22 Oct 2019

Kick-off Meeting (M1)

(9.30 to 17:30H)

22 Oct 2019

31 oct 2019

Submission of the Action Management Plan (MS 1)

10 Dec 2019

Action Coordination Meeting (M3)

Canceled

10 Dec 2019

31 Dec 2019

Deadline for data sets definition and requirements definition (completed and available for all 3 cities) (MS 2)

Delayed

31 Dec 2019

Submission of the Dissemination and Communication Strategy (MS 3)

31 Dec 2019

2 Mar 2020

Action Coordination Meeting (M6)

(10:00 to 12:30H)

30 Apr2020

Submission of the Dissemination and Communication Strategy (MS 3 Updated Version)

30 Apr2020

30 May 2020

Deadline for service and use cases full definition (completed and available for all 3 cities) (MS 4)

Delayed

31 May 2020

Data sets definition and requirements definition (completed and available for all 3 cities) (MS 2 Draft Version)

31 May 2020

22 to 24 Set 2020

Portugal Smart Cities Summit 2020

30 Set 2020

Deadline for submission of the Report on Co-Creation Labs (MS 5)

Delayed

30 Set 2020

30 Set 2020

Deadline for Analytical models disclose in public via Lisboa Aberta Portal (MS 6)

Delayed

03 Nov 2020

Action Coordination Meeting (M 12)

(10.00 to 13:00H)

03 Nov 2020

30 Nov 2020

Deadline for submission of the Report regarding the supercomputing resources that have been used (MS 7)

Delayed

30 Nov 2020

Deadline for publication of the relevant datasets, resulting from the Action on a national portal or catalogue harvested by the European Data Portal (MS 8)

Delayed

30 Nov 2020

31 Dec 2020

Data sets definition and requirements definition (completed and available for all 3 cities) (MS 2 Updated Version)

31 Dec 2020

Service and use cases full definition (completed and available for all 3 cities) (MS 4)

31 Dec 2020

31 Dec 2020

Report regarding the supercomputing resources that have been used (MS 7)

31 Jan 2021

Call for Papers for Lisboa Urban Data Lab

31 Jan 2021

23 Mar 2021

Action Coordination Meeting (M18)

(9.30 às 13:00H)

1st April to 3rd July 2021

World Data League

League: April and May 2021
Finals: July 2021

1st April to 3rd July 2021

18 to 20 May 2021

Lisboa Urban Data Lab

(Canceled)

08 July 2021

Action Coordination Meeting (M21)

(9.30 às 13:00H)

08 July 2021

30 Jul 2021

Deadline for submission of the Report for all services (identification of viable business models and willingness to buy verified) (MS 9)

Delayed

14 to 16 July 2021

Lisboa Urban Data Lab

(Canceled)

14 to 16 July 2021

7 to 10 Set 2021

5th International Conference “Urban e-Planning”

24 Set 2021

Report on legal and regulatory frameworks applicable to open data collection

24 Set 2021

27 Set to 24 Oct 2021

Innovation Dive: Urban Lab X Innovation&Analytics Lab

Student Open Challenge

11 Oct to 1 Nov 2021

Innovation Dive: Urban Lab X Innovation&Analytics Lab

Research for Empathy

11 Oct to 1 Nov 2021

15 Dec to 17 Dec 2021

Innovation Dive: Urban Lab X Innovation&Analytics Lab

Open Innovation Co-Creation

17 Dec 2021

Final Conference in Lisbon (M24 + 3)

(9.30 to 17:30H)

17 Dec 2021

31 Dec 2021

Deadline for submission of the Report on completed use cases implementation (in all cities) (MS 10)

31 Dec 2021

Deadline for submission of the Final Reach Assessment Report (MS 11)

31 Dec 2021

31 Dec 2021

Deadline for submission of the Final Conference in Lisbon Meeting Report (MS 12)

31 Dec 2021

Demonstration of the Action’s results (MS 13)

Via a remote or onsite meeting with DG CNECT ((9.30 to 13:00H)

31 Dec 2021